Next and Previous Card Relation

One of two possible card relations is the previous and next relation. Previous card must be completed before the start of the next card. Time is the essence of this relation. 

Card relations are visualized with icons:

  • previous card
  • next card

The most important features in this relation are card dates. Due date of the previous card must be earlier than the start date of the next card. Otherwise, cards will be marked with orange exclamation mark.

The best way to visualize this relation is the Gantt chart view. You can change card dates with drag&drop like on the example below.

Learn more about date dependencies observation.

FAQ

You can create previous and next card relation from the card level or using Gantt Chart view.